Gorkha, Oct 10 : A road section
linking Barpak and Laprak of Gorkha has been obstructed for the past three
months.
Problems have surfaced to transport
daily essentials to Laprak due to obstruction of the road by landslide in the
beginning of the rainy season, said locals.
Birbal Gurung of Laprak said,
"Three months have passed since the obstruction of the road section, no
initiatives have been taken to carry out repair and maintenance of the
road."
He complained that the rural
municipality has not taken any necessary efforts for the repair and maintenance
of the road section.
The upgrading work of the
Barpak-Laprak road section was started after signing a contract with a
construction company on May 22, 2020, it remain incomplete yet even after 41
months.
Infrastructure Development Office,
Gorkha, had given responsibility to the construction company—Sharma/Bikki JV to
complete the upgrading works within two years at a cost of Rs 341.57 million.
Only 52 per cent of physical progress of the project has been achieved so far,
said Office Chief, Ganesh Subedi.
The responsibility was given to the
construction company to gravel 13.14 kilometer Barpak-Laprak road section. The
deadline of the project was extended in order to complete the works within June
5, 2023, but the upgrading work has not been completed yet.
Chief Subedi shared that the
construction company has been delaying projects under various pretexts.
Difficulties have surfaced to
transport food stuffs at Laprak and Gumda as well as taking patients to
hospitals in lack of timely completion of the upgrading work. (RSS)