Khotang, July 25: Blacktopping of 49-km Mature-Foksingtar road on the Diktel-Gaighat road section along the Sagarmatha National Highway has been in limbo.
This is so far the shortest route
to link Terai districts from Diktel. The blacktopping has stagnated due to
sheer negligence on part of the contractor companies.
As informed, the Bharat
Construction Siddhi Shahi JV was entrusted with blacktopping the 22-km road
from Mature to Simpani of Rajani.
Likewise, the Devnarayan Pawan
Mainachuli Khampache JV was awarded the contract for blacktopping the 27-km
road from Simpani Bhanjyang to Foksingtar.
The road section which has to be
handed over to the Department of Roads after completing blacktopping now has
been obstructed due to potholes and muddy surfaces.
A contract was awarded to the
Bharat Construction Siddhi Shahi JV to complete the task within 13 July 2020.
District residents have been facing trouble due to the lingering blacktopping of
the road after a long time since the contract came to an end.
It has been shared that the road
section has so far made only 35 percent progress.
Likewise, blacktopping of the Timpani
Bhanjyang-Foksingtar road section has only seen 59 percent progress. The
contract to this effect was made with Devnarayan Pawan Mainachuli Khampache JV
to complete blacktopping within 26 July 2020.
The road that had been used to
transport daily essential goods and construction materials from Terai districts
has not made any progress in its blacktopping since last Mid-March.(RSS)