Kathmandu, Feb 28 : Construction of various bridges along the North-South Corridor roadways is yet to be started though there is a target to complete the Corridor projects in the next two years.
To date, the Kaligandaki corridor
awaits the construction of 15 bridges followed by five bridges along the
Karnali corridor and four in the Koshi corridor. It is said two bridges along
the Koshi corridor have been already over and two are under-construction.
Works are underway to construct 70
meters bridge along the Barun River, according to North-South Corridor project
Chief Shyam Bahadur Khadka.
As the Project briefed, the
Kalingadaki has already reported the completion of five bridges and some have
neared the completion phase. The bridges measure 60-70 meters. The Project
targets building 14 bridges there in the current fiscal year. "In overall,
15 projects await contracts."
Among the three corridors, the
Karnali reports the lowest progress where the construction of various culverts
along with bridges is awaited. A total of 14 bridges are to be constructed
along the Karnali corridor and contracts for nine were finalized till mid-July
last year while five are under-construction.(RSS)