Rasuwa, Dec 27: The progress of the
under-construction dry port at Timure in Rasuwa has received a good push with
the completion of 72 percent of the estimated task.
The dry port being developed with
the technical and financial assistance from the government of China along the
Nepal-China border has achieved 72 percent of the target, Executive Director of
Nepal Intermodel Transport Development Board Ashish Gajurel told the RSS after
the inspection visit of the project.
An embankment on the bank of
Bhotekoshi river, entrance gate, access route, buildings of the warehouse and
other facilities have been completed so far.
According to Gajurel, the project
is expected to complete by the end of the current fiscal year.
With the completion of dry port
construction, there will be a joint inspection site, parking lots for 300 heavy
trucks and 100 small-sized vehicles among other facilities. (RSS)