Madhyabindu (Nawalparasi), Oct 12 : The eastern section of the Narayangarh-Butwal road expansion project has so far witnessed sluggish physical progress.
The 64.42-km Gaindakot-Daunne road
stretch under the Butwal-Narayangarh section along the East-West Highway has
made only 41.17 percent physical progress.
The contract for the road widening
project was signed around five years ago on conditions that construction works
will be completed in three years and the contractor company shall look after
maintenance of the road.
However, the road expansion drive
has not gained momentum as anticipated despite expansion of deadline for
several times.
Project's eastern section manager
Rakesh Jha shared that overall progress of the eastern section of the project
has reached 41.17 percent.
"Daily 595 workers, including
technicians are working in the eastern section while 13 excavators, seven
graders, 11 loaders, four cranes, 28 tippers, 10 water carrying tanks and five
concrete-carrying vehicles are being regularly mobilized in the eastern section
of the project", he added.
Jha said construction works have
been intensified in the field to meet the progress in the extended timeline.
The project has also continued the task of blacktopping on the road section, he
further shared.
According to him, 16-km of the
eastern section has been so far blacktopped. "Taking into consideration
the festivals coming closer, the task of repairing the broken road has also
been taken ahead", he informed.
Information Officer and engineer at
the eastern section of the project, Dhiraj Dhakal said tasks related to small
bridges and sub-structure of 11 out of 12 large bridges on the eastern section
have been completed.
"In the eastern section,
around 50 percent tasks related to relocation of electric poles have been
completed", he said.
The 115-km road project from the
Narayani River of Gaindakot to Buwal was divided into two sections while
signing the contract for expansion. The Chinese State Engineering Corporation
was awarded the contract for the expansion project. The section 'A' includes
64.42-km road from Gaindakot to Daunne and section 'B' has 48.58-km from Daunne
to Butwal.
The road expansion project is being
implemented with 85 percent loan assurance of the Asian Development Bank (ADB).
As per the design, the road will have six lane in settlement area, four lane in
forest area and three lane in Daunne mountainous area.
As informed, the government has
invested 15 percent of the total costs of the project. (RSS)