Fast-track: 'Effective political initiative a must'

blog

Kathmandu, Feb 4: The Defense Ministry has pointed out the need for an effective political initiative to resolve the Khokana land problem in order to accelerate the construction of the Kathmandu-Tarai fast-track.

Although initiatives were taken to resolve the problem in order to accelerate the construction of the fast track, the problems have remained intact. Kathmandu-Tarai fast-track is one of the national pride projects of the country. 

In the second quarter progress review of the ministry, Chief of Army Staff, Prabhu Ram Sharma, said, "Discussion was held from ward chairpersons to Prime Minister on the issue of Khokana. There is no protest from anywhere. But the problem could not be resolved yet." 

Parliamentary monitoring was carried out time and again on the issue of land acquisition of Khokana area for the fast track and the Nepali Army has been making inter-body coordination by forming a special mechanism. 

Locals of Khokana have been protesting the construction of the fast-track with the fear of being displaced as there would be an outer ring-road, dry-port as well as other big projects at Khokana. 

The Nepali Army has got the responsibility to construct the fast track. It has been constructing the fast-track leaving the construction of around four kilometers area of the section, where locals have been continuously protesting, as the NA has to complete the project within the deadline. 

CoAS Sharma opined, "Around 80 percent of locals, out of the locals whose land is used for the construction of fast-track, have already received compensation. Only 20 per cent of locals have been protesting."

Similarly, Secretary at the Ministry, Kiran Raj Sharma, said, "Effective political initiative is necessary to resolve the Khokana land dispute." 

Altogether 5,772 ropanis of land should be acquired for the construction of fast-track, and compensation of 4,780 ropanis of land has been distributed so far. Distribution of 392 ropanis of land in the Khokana area has not been distributed due to locals protest. 

The 72.529-kilometer fast track is being constructed at an estimated cost of Rs 175 billion.  A total of Rs 29.99 billion budget has been allocated for the project in the current fiscal year. (RSS)