Kathmandu, June 9 : The Department of Roads (DoR) has
been annulling the contracts of those construction companies failing to deliver
construction of roads and bridges on time.
Although deadlines were extended
repeatedly, the negligent contractors kept on dilly-dallying the construction
works for a long time resulting in nullifying of the contracts.
According to Nareshman Shakya,
Chief of Division of Bridge under the DoR, the Department would assign
construction from the same company despite the delay. The contract would be
repealed if there is no condition for the construction company to deliver on
time.
The contract for construction of
bridge over the Trishuli River at Battar, Makaisingh in Gorkha district has
been annulled. Process to take forward the remaining works through new contract
is due, said Shakya.
"If the notice is issued in
the ongoing fiscal year, the construction work would start beginning the next
fiscal year," he said.
Not all construction companies are
negligent. Some are very responsible too. For instance, there is a construction
company that is repairing the bridge linking Dhanusha district with Siraha, he
informed. He shared that two contracts were, however, on the verge of being
annulled.
Chief Shakya shared that some
processes like publishing notice have to be fulfilled before annulling the
contract and so it will take some time to go into the process by breaking the
contract.
According to him, the same company
would be given an opportunity if the construction entrepreneur comes forward
expressing commitment to carry out the work even when the process for action is
forwarded. Shakya informed that the contract would be annulled if the progress
of work is not satisfactory or when work has not been carried out at all.
"The opportunity to continue
the work is provided to the contractor coming forward with strong
evidence," he said.
Engineer Suraj Adhikari shared that
there were several 'chronic contracts' in the under-construction 400 kilometres
road of the Mid-hills highway. He informed that the contract for the
construction of the Bheri Bridge has been rescinded some time back as the
construction works remained in limbo for long.
Five contracts have been annulled
in the current fiscal year in Panchthar. He said the contract had to be called
off after the contractor failed to carry out works despite extending the
contract many times.
The government has forwarded the
construction of the bridge over the Jabdighat Khola in Bardia hiring a new
contractor some time back after calling off the contract with the previous
one.
Similarly, the contract for the
Balaju-Trishuli road has also been annulled after it made no progress for long.
There was this practice of extending the contract period of projects, the construction of which remained stalled for long in the past years sometimes citing the COVID-19 pandemic and sometimes pointing out to the amendment of the Public Procurement Regulations.
But nowadays, not only the
Department of Roads but the Ministry of Physical Infrastructure and Transport
is also showing its interest in managing the so-called 'chronic contracts'.
Ever since he assumed the ministry portfolio, Minister Prakash Jwala has shown
his eagerness in annulling the contract of the contractors not carrying out
works and keeping the construction projects in limbo for long. (RSS)