Chitwan, March 5 : The Narayangadh-Muglin road section
will open for traffic during the afternoon starting today.
The road section used to remain
closed for 4 hours in the afternoon from 11 am to 3 pm for the purpose of
chopping off the hill side to expand the road for construction of bridges along
the roadway.
The work of making way for
construction of bridges have been completed except for the hill next to Tuin
river towards Muglin, said Krishna Acharya, information officer of
Nagadhunga-Muglin road project. Explosives are being used to blow up the hall
next to the Tuin river, where 40 meters are yet to be cut.
The work of cutting side wall was
carried out next to the Chisenji, Simaltal, Kalikhola and Namchi rivers, which
have been completed. Five bridges are under-construction along the road.
A total of 20 bridges have been
added on the road after the latest expansion of the road. (RSS)