Lamjung, Aug 22 : A breakthrough has been made in regard to the construction of a tunnel serving as the approach to the powerhouse under the 42.60-megawatt Super Nyadi Hydropower Project based in the Lamjung district. The breakthrough was made a few days ago.
The project being developed by the
Siuri Nyadi Hydro Power Company is based in Myarsyangdi rural
municipality-6.
According to project managing
director Dinesh Gurung, a 387 metres long tunnel has been readied for the
construction of a powerhouse and so far the project reports the completion of
30 per cent of work.
Likewise, works are on for digging
a major tunnel under the project.
Only 1.5 kilometres, out of 22
kilometres of dam side road, is left to be constructed and it is likely to be
finished by the next two months. The construction materials are being
transported here via a helicopter.
According to the project, the total
number of workforce deployed for the project on a daily basis is 240.
As per the Power Purchase Agreement
(PPA) signed under the project, power generation shall begin by the next two
years. High Himalaya and Dhawalagiri Construction and Development Pvt Ltd have
the contract to implement the project.
NMB bank is the leading investor
in the project while six other financial institutions will be investing Rs
5.25 billion as loans. The equity capital of promoters will be 1.75 billion.
It is expected to cost Rs 7 billion
to complete the project. Electricity to be generated from the project will be
connected to the 132 kV transmission line's Khudi Substation which lies 11
kilometres away from the powerhouse.
The transmission line up to the substation will be constructed by the project itself.
According to the project, in
winter, the power trade rate is Rs 4.80 per unit for six months in the rainy season
and Rs 8.40 per unit for six months during winter. (RSS)