Damauli, Dec 8: The eastern part of the Muglin-Pokhara road expansion project has witnessed 42 percent progress. The road expansion project is in implementation to widen the Prithvi Highway to four lane.
The progress has been made in the
road section stretching from Anbukhaireni to Jamune of Tanahun.
Project's eastern section Engineer
Bishnu Prasad Pandey informed that the task of blacktopping has started along
the expanded section of the road. He shared that one way blacktopping has been
so far done on nine kilometers section of the 41.5-km stretch.
Likewise, the task of blacktopping
additional five kilometers road has started since Wednesday.
The blacktopping of the road from
Anbukhaireni rural municipality-3, Gaunpalika Chowk to Markichowk has started,
he shared.
Earlier, blacktopping of 3.5
kilometers road section from Anbukhaireni-1 Satrashaya to Markichowk was
completed.
According to the project source,
the task of blacktopping has advanced in a way to complete it within next 15
days. (RSS)