Lumbini (Marchawar), Jan 27: Almost
40 percent of the work of electricity substation being constructed in Marchwar
area of Rupandehi has been completed.
Nepal Electricity Authority (NEA)
has shared the power supply in the area will improve permanently after the
construction of Mahadei Substation at Marchwar, which is being constructed
targeting the three municipalities.
According to NEA engineer Jagadish
Raj Baral, 35 percent of the civil structure and 40 percent of the
electrification work of Mahdei substation have been completed.
The remaining works of the project
are progressing at a rapid pace to meet the target to complete it within a
year, he added.
He shared that the agreement was
signed with the construction company on last February. "We are planning to
complete the project within the next one year and bring the substation into
operation," he said.
The construction work has been
delayed due to lack of soil testing, paperwork and various materials at the
site, NEA engineer Baral said, adding that most of the materials required for
the construction of the substation have been managed. Planning Manager at the
construction company, Mukul Singh said that the project could not be completed
on time due to delay in the design of the project.
After receiving the design, a team
of 40 people has completed the installation of 850 electric poles so far, he
said.
The NEA has stepped up routine
monitoring of the substation construction works so as to ensure reforms in
power supply. (RSS)