Tanahun hydropower project sees above 50 per cent progress

blog

Damauli (Tanahun), Oct 20: The Tanahun hydropower project with a capacity of 140 MW has achieved a progress of 58.1 percent.    
    
The work on the hydel is being carried out in three package, and 52.07 percent financial progress has been achieved, said project chief Shyamji Bhandari.    
    
Likewise, 35 percent progress has been made in the construction of structures including dams under package-1. 59 percent progress in the construction of power plants under package-2 and 73.5 percent of the construction of transmission line under package-3.    
    
The goal is to complete the project in the next two years, by Asar 2083 BS. The supply, installation and operation of hydromechanics and electromechanical equipment, as well as the construction of tunnels and powerhouses are underway.    
    
Under package-3, the KEC International company of India is constructing a 220 kV double circuit transmission line from Damauli to Bharatpur in Chitwan. (RSS)      


How did you feel after reading this news?

More from Author

Visiting Chinese delegation calls on PM Oli

Tourism entrepreneur Mishra passes away

Woman killed, 26 injured in road accident

Nepal tour of US: Nepal posts 170 in 20 overs

3.58 billion revenue collected in 3 months