Damauli (Tanahun), Jan 26 : Blacktopping has started in the west section of Tanahun under the Muglin-Pokhara road expansion project.
The Muglin-Pokhara road project
(west section) has begun blacktopping the road from Shuklagandaki
municipality-2, Haledi of the district under the Jamune-Pokhara.
Road Section's engineer and
Information Officer Narayan Poudel shared that 420-meter one-way blacktopping
was done first day on Thursday. According to him, the target is to blacktop the
one-way five kilometer section by coming March 13.
He further shared that blacktopping will also be carried out from Jamune of Myagde rural municipality and Belchautara of Shuklagandaki municipality from today onward. "Now the work will be expedited and the blacktopping work will continue. Necessary human resource and equipment are ready".
In the first phase, only one-way
blacktopping will be done and two-way will be taken ahead once the one-way work
goes ahead, he said.
The road project has taken forward
the blacktopping using asphalt technology. Under the western section, the work
from Jamun to Pokhara had started from 29 August 2021 after signing an
agreement on 14 May 2021.
The contract for the construction
of the section was awarded to the Chinese Company, Yanhui Kaiyun Highway and
Bridge Construction at a cost of Rs 7.40 billion. The deadline for completing
the construction of the western section is August 2024.
Shankar Panta, a local, said they
have become optimistic after the blacktopping started. "The locals who
were fed up with the dust and mud on the road are happy with blacktopping work
making progress after a long time since the road expansion started," he
said.
He further said they would also
continuously monitor to ensure quality in the construction works.
The work progress in the section of
the Muglin-Pokhara road expansion project has been quite a slow.
As shared, materials needed for
blacktopping 20-km section in the western part has been arranged.
Likewise, around 20-km section of
the eastern section has already been blacktopped. The contract for the eastern
section was awarded to the China Communications Construction. It has the
deadline up to mid-May 2024.