Bharatpur, Jan 8 : Service-recipients are deprived of service as the charging station based at Muglin Bazaar, Ichhakamana rural municipality-5, Chitwan, remains dysfunctional nearly for two months.
It is said that the charging nozzle
of the charging station has broken and two DC chargers are dysfunctional less
than a year since the station was installed. Only one AC charger is functioning
at present. It takes long time to charge vehicles only from the AC charger, it
is said.
Dhruba Gurung of Gorkha who came to
charge his car complained that service-seekers including himself have been
facing problem as the charging station here still remains unrepaired. As he
said, one has to wait for hours on end charging vehicles using AC charger. He
said his vehicle is charged only six per cent in 20 minutes.
"The vehicle used to be fully
charged in one hour when the charging station was functioning. Now, one has to
wait for 2-3 hours to fully charge the car," he expressed his dismay.
He complained that although the
government has emphasized on using electric vehicles, it has not paid attention
to constructing additional charging stations and repairing the dysfunctional
ones in time.
According to him, people have to
wait in queue for many hours to charge their vehicles since there are not
enough charging stations.
Shiva Adhikari, project manager of
Digo, the company which is responsible for constructing the charging station,
said that the problem is due to the broken charging nozzle and they have already
ordered for the required spares that need to be changed. He added that the
equipment would be arriving in a day or two.
He said the repairing works would
be carried out in a day or two by dispatching a technical team.
Adhikari said 62 charging stations
have been installed throughout the country through the Nepal Electricity
Authority (NEA). He stated problems have been detected in 20 of them. (RSS)