Damauli, June 5 : Structures based in Bandipur rural
municipality-1, Dumre of Tanahun are being demolished as part of the Prithvi
highway expansion plan.
A drive has begun to break down
houses and huts that were constructed within the road section.
According to engineer of
Muglin-Pokhara Road Project (Eastern Section) Bishnu Pandey, five houses of
Dumre Bazaar – the main commercial hub of Bandipur and entry point to Lamjung
district – are being razed now.
'The drive is underway to remove
structures built within the road territory. As of now, five houses have been
razed', he informed, adding, 'All the structures constructed within the road
scope would be gradually demolished'.
Most of the houses built long back
in Dumre Bazaar were found within the road area. A plan was mooted to raze such
structures by providing compensation.
The eastern part includes
Anbukhaireni rural municipality, Bandipur rural municipality and Byas
municipality.
Preparation is also being made to
remove the structures built in Anbukhaireni and Byas.
He further informed as many as 631
structures would be removed from the section. Compensation amounting to Rs
2.245 million would be distributed to the rightful owner.
The Muglin-Pokhara Road Expansion
Project has expedited its works in two sections. The eastern section from
Anbukhaireni to Jamune has made 30 percent progress, the project sources said.
Blacktopping has started in seven-kilometer section of Anbukhaireni.
Project chief Narendra Subedi said
tht works have been expedited with a target to complete blacktopping of
seven-kilometer in the current fiscal year.
The expansion drive was initiated
in the eastern section in April 2021 after contract signing for the same in
January 2021. In the 41.45-km road section, three big and four small bridges
would be constructed. The contract was awarded to China Communication
Construction for the eastern section.
The government this year has
allocated a budget of Rs 5.42 million for the Muglin-Pokhara road
expansion.
The four-lane road is being
constructed with the loan assistance of the Asian Development Bank.
The contract of Rs 6 billion 231
million was signed for the eastern section while it was Rs 7 billion 44.6
million for the expansion of western section. The four-lane road section will
have 20-25 meter in each side. (RSS)