Nawalpur, Sept 26 : As the construction works along the Narayanghat-Butwal road section of the East West Highway remained intolerably slow, the government has warned the contractor of contract termination.
Issuing a notice
on Sunday, the South Asia Sub-Regional Economic Cooperation Road Connectivity
Project of the Department of Roads said that the contract agreement would be
terminated if the existing way of working of the contractor was not
improved.
The 114
kilometres of road stretch was separated in two sections while awarding the
contract through a global bidding process. The China State Construction
Engineering Corporation Limited had won the tender bidding of both section for
pledging to construct the road section in the minimum base rate.
It is said that
several complaints were received on the part of the construction company
regarding the dillydallying of the project.
The project was
expected to complete in August 7, 2022. However, the construction company
completed just 18 per cent of the total task in the final deadline.
Against this
backdrop, the Department of Roads has warned to construction company to mend
its ways and ensure reforms in a month otherwise get ready to face contract
termination.
The Department
has further said that the travelers and vehicles have faced several issues
including difficulties in travel, air pollution and others due to carelessness
of the construction company.
The community
people in the affected area have also suffered while road accidents have
soared.
As the contract
agreement ended on August 7, the government has extended the deadline for one
more year at the request of the construction company but the construction works
at present have halted, Chief Engineer of Narayanghat-Butwal Road Project (Eastern
Section) Ramesh Kumar Dristi said.
The project
being developed with nearly Rs 17 billion in loan assistance from the Asian
Development Bank. (RSS)