Triveni (Nawalparasi), Jan 24 : Only 45 percent of the works has been so far completed in Nawalparasi eastern section under the Narayangadh-Butwal road expansion project.
Over half of the project work is
yet to be completed with about six months left for the deadline to expire, Road
Expansion Project's eastern section chief Ashish Thapa Magar said.
The Narayangadh-Butwal road
expansion work had initiated in 2075 BS. Since then, the deadline has been
extended twice. The second extension will expire in coming mid-July.
He further shared that 90 per cent
of the work will believably be completed during the period. According to him,
the construction company will be responsible for repair for five years even
after the construction of the project, so the progress should be 90 percent by
mid-July considering post-construction repair work as about 10 percent.
"Looking at the current
physical progress, at least monthly seven percent progress has to be made to
complete the road expansion work on time. However, the work progress is
sluggish, Magar said. "We have been repeatedly instructing the contractor
to speed up the work", Magar added.
Stating that the manpower and
machinery used at present are insufficient, he said that the China State
Construction Engineering Corporation, the contractor, is being directed to
complete the work within the stipulated time using adequate resources.
According to him, the pace at which
the progress should have been achieved is low. The 113-km Narayangadh-Butwal
section of the East-West Highway covers about 65 kilometres in the Middle East
section.
A six-lane road will be constructed
in the market area with service lanes, three in Daunne section and four lanes
in other areas. So far, only 21 kilometers of two-lane road has been completed
in the eastern section.
About 125 kilometers of road has to be constructed
after calculating the two-lane road except the part of the bridge. In this way,
more than 100 kilometers of blacktopping is yet to be done. "The blacktopping
of about 21 kilometers has been completed by calculating the one-way
calculation," the project chief said.