Nawalpur, Dec 27 : The task of
blacktopping in the eastern section of Narayangarh-Butwal road stretch along
the East-West Highway has gained momentum.
Blacktopping has completed in 18.5
kilometers out of 65 kilometers from Gaidnakot to Daunne in the eastern
section.
According to contract manager of
the China State Construction Engineering Corporation Limited Rakesh Jha, one
side blacktopping with sub-base, construction of large bridges and walls along
the road stretch and rivulet banks are being carried out.
He informed that road expansion
works are being carried out in a way to complete one-side blacktopping in 42-km
section in next two months.
He shared that emphasis has been
laid on expediting the construction of big structures along the road.
"Four out of five kilometers
in Daunne has been expanded by cutting the mountain area", her said,
adding, "Works are being expedited to complete soil cutting in remaining
one kilometer section in next one month".
Now the road expansion has gained
momentum from Bhedabari to Jharahi khola of Gandakot as well as in Rajahar of
Devchuli, Danda Bazaar of Kawaswoti and Kawaswoti Bazaar area.