By A Staff Reporter
Kathmandu, Sept. 12: The physical construction work at the Gautam Buddha International Airport (GBIA) in Bhairahawa has almost completed with 92 per cent progress.
The construction work has completed and installation of lights and equipment is underway at the site, said the Ministry of Culture, Tourism and Civil Aviation.
The contractors -- Civil Aviation Airport Construction Group, China and Aeronautical Radio of Thailand Limited -- have continued the construction work even during the COVID-19 pandemic.
According to the project, although most of the equipment has arrived at the site, the human resource management has become challenging due to the constraints in the international flights because of the pandemic. About 275 workers had been working even during the lockdown period.
Conveyor belt and some electrical items for the runway and taxiway have arrived at the construction site while some are on the way.
The ministry has started the process to bring in 35 Chinese technicians/engineers.
Construction of the GBIA had begun in 2015 with the target to complete it by the end of 2017. The deadline was extended till March 2020, however, it was again delayed.
The Rs. 7.32 billion project is not likely to come into operation in the next six months.
Do not make expressions casting dout on election: EC
14 Apr, 2022CM Bhatta says may New Year 2079 BS inspire positive thinking
14 Apr, 2022Three new cases, 44 recoveries in 24 hours
14 Apr, 2022689 climbers of 84 teams so far acquire permits for climbing various peaks this spring season
14 Apr, 2022How the rising cost of living crisis is impacting Nepal
14 Apr, 2022US military confirms an interstellar meteor collided with Earth
14 Apr, 2022Valneva Covid vaccine approved for use in UK
14 Apr, 2022Chair Prachanda highlights need of unity among Maoist, Communist forces
14 Apr, 2022Ranbir Kapoor and Alia Bhatt: Bollywood toasts star couple on wedding
14 Apr, 2022President Bhandari confers decorations (Photo Feature)
14 Apr, 2022